References

“Trust is built on actions, not on words.“

References: Engineering and New Power Plants

  • Germany: Duisburg
    • Project consulting and coordination of technology for a new power plant based on two GE gas turbines, type MS 6001 FA
  • Kazakhstan: Karachaganak
    • Project management for two GE gas turbines, type MS 6001 B (40 MW each)
    • Front End Engineering Design FEED and feasibility study for the 4th gas turbine generator set, type MS 6001 B
  • Iraq: Arbeel
    • Simple-cycle gas turbine project, 4 x GE gas turbine, type Frame 9E (120 MW each)
    • Mechanical balance of plant engineering, layout und project management
  • Austria: TBA Arnoldstein (1)
    • Waste Incineration Plant, el. Power: 5MWel, District Heat up to 9MWth
  • Austria: Power Plant Donaustadt (1)
    • Combined Cycle Power Plant, 367 MW el. Power, 250 MW District Heat
  • Austria: Power Plant Simmering (1), (2)
    • Combined Cycle Power Plant, Block: 4: 540 MW, Block 5: 860 MW
    • Civil Construction & Infrastructure, Projectmanagement, Installation of Heat Recovery, Steam Generators, Complete Balance of Plant
  • Austria: MVA Pfaffenau (1), (2)
    • Waste Incineration Plant, el. Power: 65 GWh / year, 10 MW Steam Turbine, District Heat: 410 GWh / year
    • Civil Construction & Infrastructure, General Contractor for Flue Gas Cleaning Station SCR DENOx Station, Balance of Plant
  • Austria: Thermal Power Plant Dürnrohr (1), (2)
    • Coal Fired Power Plant, el. Power: 750 MW
    • Fire Fighting System, DeNOx & Catalytic Dedioxin-Station
  • Austria: VOEST, Block 7 (2)
    • Furnace Gas Fired Boiler - Power Plant, BoP Design, Engineering & Supply incl. Turbine Piping & Installation of Boiler
  • Germany: Südwest-Thüringen RABA - Suhl (2)
    • Waste Incineration Plant
    • Engineering, Supervision & Documentation
  • Germany: Zellstoff Stendal GmbH (2)
    • Complete Piping of the paper mill energy supply plant
  • Germany: Industriepark Höchst (2)
    • Combined Cycle Power Plant
    • Engineering & Supply of BoP (Water Steam Cycle) & ST Installation 
  • Denmark: SCR Studstrupvaerket (2)
    • DeNOx-Station
    • Burmeister & Wain Energy A/S
  • Spain: Tirmadrid (2) 
    • DeNOx - Station
  • China: Guangzhou, Dalian & Shanghai (2)
    • 3 Gas-Splitting-Stations
    • EPC Contractor, Process Engineering, repsonsibility for Guarantees & Performances, Supply of Key Components & Equipment, Comprising Catalyst Steam Turbine & Blowers, Combustion Burners, complete Automation, Supervision of Erection, Complete Comissioning & Performance Test

(1) = Porr
(2) = Integral

 

References: Relocation and Commissioning

  • Relocation of a power plant from Thailand to Sudan
    • Relocation of three GE gas turbines, type MS 6001 B (40 MW each)
    • Mechanical & electrical engineering including auxiliaries
  • Relocation of a power plant from Sweden to Angola
    • Turnkey relocation of a gas turbine, type GT 200 (82 MW)
    • Plant dismantling, re-installation, commissioning, operator training
    • Major overhaul of the generator
  • Netherlands (Rotterdam)
    • Installation and commissioning of two GE gas turbines, type MS 6001 FA (126 MW each) including auxiliaries
  • Germany (Munich)
    • Turnkey installation of two GE gas turbines, type MS 9171 E (126 MW each) including piping and electrical supplies
  • Germany (Duisburg)
    • Turnkey installation of two GE gas turbines, type MS 6001 FA+e (75 MW each) including piping and electrical supplies

 

   